12 men working 8 hours a day dig a 360 m trench in 18 days. In how many days will 16 men working 9 hours a day dig 480 m?

Competition practiceTime & Work / Pipes
  • A16 days
  • B18 days
  • C20 days
  • D12 days

Step-by-Step Solution

Man-hours per metre: . 480 m needs 2304 man-hours; per day : 16 days.
Answer: A) 16 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

3 men or 5 women can do a job in 12 days. How long will 6 men and 5 women take?2 men and 3 women finish a job in 10 days; 3 men and 2 women finish it in 8 days. How…8 men or 12 women finish a job in 25 days. How long will 6 men and 12 women take?6 men and 8 boys finish a job in 10 days; 26 men and 48 boys finish it in 2 days. How…4 men = 6 women = 9 boys in work. 4 men finish a job in 27 days. How long will 2 men, 3…