12 workers complete a job in 9 days working 8 hours a day. How many days will 8 workers take to complete the same job working 6 hours a day, at the same rate?

Competition practiceTime & Work / Pipes
  • A24
  • B18
  • C16
  • D20

Step-by-Step Solution

Total work = 8 = 864 worker-hours; per day worker-hours, so 864/48 = 18 days.
Answer: B) 18

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

One motor pump can fill a gram panchayat tank in 55 hours and a second pump can fill it…An inlet fills an empty overhead tank in Coimbatore in 4 hours, while a leaky valve can…Two hosepipes fill a large terrace garden tank: the first alone in 60 minutes, the…Rekha can type a project report in 14 hours and Sunita can type it in 42 hours. If they…Leela can stitch a set of curtains in 25 days and Manju in 40 days. They work together…