4 men and 6 women finish a job in 8 days; 3 men and 7 women finish it in 10 days. How long will 10 women take?

Competition practiceTime & Work / Pipes
  • A36 days
  • B35 days
  • C40 days
  • D50 days

Step-by-Step Solution

Multiply to and . 10 women do a day.
Answer: C) 40 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

10 workers build a 120 m wall in 12 days working 8 hours a day. How many hours a day…25 men were to finish a job in 30 days. After 20 days only half was done. How many extra…A works 6 hours a day and finishes a job in 16 days; B works 8 hours a day and finishes…3 men do as much as 4 women, and 2 women as much as 3 boys. 4 men finish a job in 18…A takes 8 days and B 12 days for a job. They work on alternate days, A first. How many…