6 women can complete a piece of work in 24 days, and 8 men can complete the same work in 12 days. In how many days can 6 women and 8 men working together complete the work?

Competition practiceTime & Work / Pipes
  • A6
  • B9
  • C10
  • D8

Step-by-Step Solution

6 women do 1/24 per day and 8 men do 1/12 per day; together 1/24 + 1/12 = 1/8 per day, so 8 days.
Answer: D) 8

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A village pond is filled by two canals; one alone would take 14 hours and the other…A carpenter in Saharanpur can finish an order of wooden stools in 60 days, and his…Sushma can paint the classroom walls of a primary school in 70 days, and Kamla can do it…A plumber and his apprentice together fit the pipes of a new house in 30 days. The…24 labourers can dig an irrigation canal in 35 days. If 28 labourers are employed…