A, B and C take 20, 30 and 60 days. All start; A leaves after 4 days and B after 8 days; C finishes. How many days does the job take in all?

Competition practiceTime & Work / Pipes
  • A28 days
  • B30 days
  • C32 days
  • D36 days

Step-by-Step Solution

In units of 60: A 3, B 2, C 1 a day. 4 days all: 24. Days 5–8, B and C: 12. Left 24 for C: 24 days. Total 32.
Answer: C) 32 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

4 men and 4 women finish a job in 3 days; 2 men and 5 women in 4 days. How long would 1…Taps A (3 h), B (4 h) fill a tank and C (6 h) empties it. They are opened at 1 p.m., 2…A and B take 6 days, B and C 10 days, and C and A 15 days. Taking the job as 30 units,…5 cats catch 5 rats in 5 minutes. How many cats are needed to catch 100 rats in 100…Two pipes fill a tank in 12 and 18 minutes. A drain removing 4 litres a minute is also…