- A14
- B13
- C15
- D12
Step-by-Step Solution
In 5 days A does 5/20 = 1/4; remaining 3/4 at combined rate 1/20 + 1/30 = 1/12 takes (3/4) ÷ (1/12) = 9 days; total = 5 + 9 = 14 days.
Answer: A) 14