A contractor employs 100 men to build a hall in 50 days. After 30 days, 3/5 of it is done. How many more men does he need to finish on time?

Competition practiceTime & Work / Pipes
  • A20 more
  • B25 more
  • C50 more
  • DNone: the work is on schedule

Step-by-Step Solution

3000 man-days did , so the job is 5000. The last 2000 in 20 days needs exactly 100 men.
Answer: D) None: the work is on schedule

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A (12 days) starts a job; B (18 days) joins after 3 days and C (36 days) after a further…A (6 days) and B (9 days) work on alternate days, B first. How many days does the job…A (10 days) and B (15 days) start a job; after 2 days C (20 days) joins; after 2 more…An inlet fills a tank in 3 hours and an outlet empties it in 4. They are opened…Two people work together on a job. Which statement is always true?