A is twice as efficient as B. Working together they complete a piece of work in 12 days. In how many days can B alone complete the work?

Competition practiceTime & Work / Pipes
  • A36
  • B24
  • C30
  • D18

Step-by-Step Solution

Let B's rate be ; then A's rate is , so combined , giving ; B alone takes 36 days.
Answer: A) 36

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A can complete a work in 10 days. He works for 4 days and then leaves. B completes the…Two pipes A and B can fill a tank in 20 minutes and 30 minutes respectively. Both are…Kiran can iron a pile of school uniforms in 12 hours and Lata can do it in 28 hours.…Pooja and Rani together pack a large online order in 18 days. Pooja alone would take 45…15 workers can build a wall in 20 days. Working at the same rate, how many days will 25…