Practice30Create account

Cable-laying teams X and Y together can lay a stretch in 9 days; teams Y and Z together can lay it in 12 days; teams X and Z together can lay it in 18 days. In how many days can all three teams lay the stretch working together?

Competition practiceTime & Work / Pipes
  • A4 days
  • B13 days
  • C39 days
  • D8 days

Step-by-Step Solution

Adding the three pair-rates: 1/9 + 1/12 + 1/18 = 4/36 + 3/36 + 2/36 = 1/4. Every team has been counted twice in that sum, so X + Y + Z = 1/8 of the stretch a day, giving 8 days. 4 days forgets to halve and treats 1/4 as the three-team rate. 39 days adds the day-counts 9 + 12 + 18, which adds times instead of rates. 13 days averages the three day-counts, which is not how rates combine either.
Answer: D) 8 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A set of records was to be keyed in by a certain number of clerks in 12 days. Had 4 more…In a day 2 men do as much work as 3 women, and 3 women do as much as 5 children. If 4…Two taps fill a storage drum in 36 minutes and 45 minutes respectively when each works…Kavita is 25% more efficient than Lalit. Working together they finish a stock-taking…Deepak alone can whitewash a community hall in 33 days and Eshwar alone in 22 days. They…