Nikhil and Om together can lay a footpath in 24 days. They work together for 16 days, then Om leaves and Nikhil completes the rest in 20 more days. In how many days could Om do the whole job alone?

Competition practiceTime & Work / Pipes
  • A40 days
  • B60 days
  • C30 days
  • D48 days

Step-by-Step Solution

In 16 days they finish 16/24 = 2/3. Nikhil does the remaining 1/3 in 20 days, so Nikhil alone needs 60 days. Om's rate = 1/24 − 1/60 = 3/120 = 1/40, so Om alone takes 40 days.
Answer: A) 40 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A and B can do a job in 20 days. A works 10 days alone and then B finishes it in 30…A can do a job in 9 days and B in 12 days. They work on alternate days, A first. How…A can do 40% of a job in 8 days and B 25% of it in 10 days. Each works 5 days, one after…A, B and C can do a job in 10, 15 and 30 days. On day 1 A works alone, on day 2 A and B,…A and B can do a job in 72 days, B and C in 120 days, A and C in 90 days. How long would…