P is 50% more efficient than Q. Together they complete a task in 18 days. How many days would P alone take?

Competition practiceTime & Work / Pipes
  • A30
  • B45
  • C27
  • D36

Step-by-Step Solution

Let Q do 2 units/day; P does 3. Task = units. P alone: 90/3 = 30 days.
Answer: A) 30

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A borewell pump fills a farm tank in 34 hours, but a faulty valve can empty the full…A tap alone fills a sump in 11 hours, but because of a leak the sump takes 13 hours to…Pipes P and Q fill a tank in 24 minutes and 36 minutes respectively. Both are opened…A is twice as efficient as B, and together they finish a piece of work in 12 days. In…15 workers can build a wall in 8 days. How many workers are needed to build the same…