- A12 days
- B13 days
- C7 days
- D27 days
Step-by-Step Solution
Take the consignment as 84 units: Ramesh 3/day, Suresh 4/day, Vikas 2/day. In six days Ramesh and Suresh bind units, leaving 42. Suresh and Vikas then manage 4 + 2 = 6 units a day, so they need 42 ÷ 6 = 7 more days. Total 6 + 7 = 13 days. 12 days assumes Vikas simply replaces Ramesh at the same rate, keeping the pair at 7/day for the whole 84 units. 7 days is only the closing stretch, with the first six days forgotten. 27 days has Vikas finishing the leftover alone , overlooking that Suresh stays on the job.
Answer: B) 13 days