Tarun alone can build a garden shed in 16 days, while Uday alone needs 48 days. They start together, but Tarun leaves after 6 days. How many more days will Uday take to complete the shed?

Competition practiceTime & Work / Pipes
  • A24
  • B18
  • C30
  • D36

Step-by-Step Solution

In 6 days they finish . Uday completes the other half at 1/48 per day in 24 days.
Answer: A) 24

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

Ravi works three times as fast as Sohan. Together they finish a job in 9 days. How many…A hotel's water tank is filled by an inlet in 7 hours and emptied by an outlet in 21…Pipe P fills a tank in 16 minutes and pipe Q in 24 minutes. Both are opened together,…A is twice as efficient as B. Working together they finish a job in 12 days. How many…A can do a work in 20 days. He works alone for 5 days and then B finishes the remaining…