To dig a village pond, 18 labourers need 10 days. Working at the same rate, how many days would 15 labourers need?

Competition practiceTime & Work / Pipes
  • A12
  • B8
  • C13
  • D15

Step-by-Step Solution

Total work = labourer-days; with 15 labourers it takes 180/15 = 12 days.
Answer: A) 12

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A is twice as efficient as B. Working together they complete a work in 12 days. In how…A borewell pump fills a farm storage tank in 24 hours, but a loose joint can drain the…Working as a pair, Tenzing and Pema stitch a batch of school bags in 20 hours. Pema…An overhead tank fills through its inlet in 12 hours, and its outlet can empty it when…Two motors pump water into a temple tank in Madurai: one alone needs 15 minutes, the…