- A22.5
- B48
- C24
- D20
Step-by-Step Solution
Together they do 1/36 + 1/60 = 5/180 + 3/180 = 8/180 = 2/45 of the job per day, so 45/2 = 22.5 days.
Answer: A) 22.5