- A18
- B30
- C36
- D24
Step-by-Step Solution
The job is man-days. In 12 days man-days are done, leaving 360 for 15 men, i.e. 360/15 = 24 more days. The 18 days still left on the schedule would only be enough for 20 men; and 36 is the total length of the job (12 + 24), not the extra time asked for.
Answer: D) 24