A gang of masons can build a boundary wall in 24 days working at a steady rate. They keep that rate for the first 9 days, but from the 10th day onward the monsoon cuts their daily output to two-thirds of what it was. The wall is finished in how many days altogether?

Competition practiceRatio, Percentage & Commercial Math
  • A29
  • B33
  • C31.5
  • D36

Step-by-Step Solution

In 9 days they finish 9/24 = 3/8 of the wall, so 5/8 is left — the equivalent of 15 more days at the old rate. At two-thirds of that rate the same stretch takes days, giving 9 + 22.5 = 31.5 days in all. (Cutting output to two-thirds multiplies the time by 3/2, not by 4/3: adding only a third more time gives 9 + 20 = 29 days. Stretching the WHOLE 24 days by 3/2 gives 36 and ignores the nine good days; 33 restarts the full 24-day clock on day 9.)
Answer: C) 31.5

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Ratio, Percentage & Commercial Math practice questions

More Ratio, Percentage & Commercial Math practice

A milk tanker runs the 180 km from a chilling centre to the city at a steady 60 km/h.…A grain trader sells at cost price, but on every second sale he weighs with a stamped '1…A goods lorry is scheduled to cover 240 km in 4 hours but leaves the depot 48 minutes…A rice mill's husking machine loses 20% of its value in the first year and 10% of its…A department store's coupon reads: '30% off on the part of your bill above ₹1000.' A…