20 men can dig a canal in 18 days. After working 6 days, 10 more men join. In how many more days is the work finished?

Class 8Direct and Inverse ProportionsDirect and Inverse Proportions
  • A9
  • B8
  • C7
  • D16

Step-by-Step Solution

Total work = man-days. In 6 days, 20 men do man-days, leaving 360 - 120 = 240. Now 30 men work: more days.
Answer: B) 8

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Direct and Inverse Proportions practice questions

More Class 8 Direct and Inverse Proportions practice

If two quantities x and y are in direct proportion, then x_1/y_1 equals:If two quantities are in inverse proportion, then the relation between two pairs is:A train running at uniform speed covers 360 km in 4 hours. How far (in km) will it go in…12 pumps can empty a reservoir in 20 hours. How many pumps are needed to empty it in 16…The cost of 9 identical chairs is 5400 rupees. What is the cost (in rupees) of 13 such…