A contractor estimated that 10 labourers would finish a road in 24 days. Only 8 labourers turned up. How many days will they now take?

Class 8Direct and Inverse ProportionsDirect and Inverse Proportions
  • A33
  • B27
  • C30
  • D60

Step-by-Step Solution

Labourers and days are inversely proportional. Work = labourer-days. With 8 labourers: days.
Answer: C) 30

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Direct and Inverse Proportions practice questions

More Class 8 Direct and Inverse Proportions practice

If the weight of 65 books is 13 kg, what is the weight (in kg) of 25 such books?A car uses 9 litres of petrol to travel 117 km. How many litres are needed for a 195 km…6 taps can fill a tank in 4 hours. Because of a fault, only 4 taps work. By how many…In the table, x and y vary directly. What number should replace the "?"?The graph shows the cost of rice at a ration shop in Bhopal. Cost is in direct…