Class 8 Sharing Work and Wages — practice questions with answers
Direct and Inverse Proportions · 5 sample questions from the school syllabus. Try each one, then open the answer and the worked solution.
1. A can do a job in 10 days and B in 15 days. They do it together and earn Rs 1,500. What is A's share?
ARs 600
BRs 750
CRs 1,000
DRs 900
Show answer
Answer: D) Rs 900
Pay is shared in the ratio of work done. Rates 101:151=3:2. A gets 53×1500=900.
2. A can do a job in 15 days. A and B together earn Rs 3,000 for it and finish in 10 days. What is B's share?
ARs 2,000
BRs 1,000
CRs 1,500
DRs 1,200
Show answer
Answer: B) Rs 1,000
In 10 days A does 1510=32, so B does 31: Rs 1,000.
3. A and B share Rs 720 for a job in the ratio of the work they did. A did 5/8 of the work. What does B get?
ARs 450
BRs 360
CRs 270
DRs 320
Show answer
Answer: C) Rs 270
B did 83: 83×720=270.
4. A job was planned for 30 workers in 25 days. After 10 days, 5 workers left. How many days late was the job finished?
A5 days
B2 days
C3 days
D18 days
Show answer
Answer: C) 3 days
Left: 30×15=450 worker-days for 25 workers = 18 days, planned 15. Late by 3 days.
5. Anita and Babli sew uniforms for a school. Anita alone would take 15 days and Babli 10 days. They sew together and are paid Rs 5,000 in all. What is Anita's share?
ARs 3,000
BRs 2,500
CRs 1,500
DRs 2,000
Show answer
Answer: D) Rs 2,000
Rates 151:101=2:3. Anita gets 52×5000=2000. The slower worker earns less.