A tailoring unit in Tiruppur has three stitching machines. The chart shows how many shirts each machine stitches in one day. If all three run together at these rates, how many hours will they take for an order of 416 shirts?

Class 8Time and WorkDirect and Inverse Proportions
  • A2 hours
  • B26 hours
  • C8 hours
  • D16 hours

Step-by-Step Solution

Per hour: A , B , C shirts, together 26 shirts an hour. Time hours.
Answer: D) 16 hours

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time and Work practice questions

More Class 8 Time and Work practice

Anil and Bhola start a job together. The timeline shows when Anil leaves; Bhola then…Raju is filling the water tank shown, which already has some water, by carrying buckets…The table shows how long each worker took to do one-fifth of the same job. If Anil, Bala…The workers shown can build a compound wall in the planned number of days. The owner…Asha, Bunty and Chetan together did a job, and the pie chart shows the share of the work…