A can do a piece of work in 10 days and B can do it in 15 days. They work together for 4 days. What fraction of the work is left unfinished?

Competition practiceTime & Work / Pipes
  • A1/6
  • B2/3
  • C1/3
  • D1/4

Step-by-Step Solution

Combined rate = 1/10 + 1/15 = 1/6 per day; in 4 days they do 4/6 = 2/3, so 1/3 is left.
Answer: C) 1/3

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A is twice as efficient as B. Working together, A and B complete a piece of work in 8…12 workers complete a job in 9 days working 8 hours a day. How many days will 8 workers…One motor pump can fill a gram panchayat tank in 55 hours and a second pump can fill it…An inlet fills an empty overhead tank in Coimbatore in 4 hours, while a leaky valve can…Two hosepipes fill a large terrace garden tank: the first alone in 60 minutes, the…