A can do a work in 15 days and B in 10 days. They work on alternate days, with A starting on the first day. In how many days will the work be completed?

Competition practiceTime & Work / Pipes
  • A11
  • B13
  • C12
  • D12.5

Step-by-Step Solution

Take total work as 30 units; A does 2 units/day, B does 3 units/day, so each 2-day pair adds 5 units. Six pairs (12 days) give exactly 30 units.
Answer: C) 12

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

6 women can complete a piece of work in 24 days, and 8 men can complete the same work in…A village pond is filled by two canals; one alone would take 14 hours and the other…A carpenter in Saharanpur can finish an order of wooden stools in 60 days, and his…Sushma can paint the classroom walls of a primary school in 70 days, and Kamla can do it…A plumber and his apprentice together fit the pipes of a new house in 30 days. The…