A can finish a work in 12 days and B in 16 days. A starts; A and B work on alternate days. In how many days will the work be done?

Competition practiceTime & Work / Pipes
  • A13 3/4 days
  • B13 2/3 days
  • C14 days
  • D13 days

Step-by-Step Solution

Each pair of days: . After 6 pairs (12 days): . Day 13 (A) adds 4 to reach 46. Day 14 (B) needs 2 of its 3 parts: of a day. Total days.
Answer: B) 13 2/3 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A can do a work in 16 days and B in 24 days. A works every day, but B helps only on…A can do a piece of work in 30 days, B in 40 days, C in 60 days. A and B work for 6…A can do a work in 24 days. After A has worked 6 days, B joins, and they finish in 8…A can finish a work in 6 days and B in 9 days. They work together for 2 days; then C…15 men working 8 hours a day finish a job in 20 days. How many men are needed to finish…