Practice30Create account

A can finish a work in 6 days and B in 9 days. They work together for 2 days; then C joins and the work is finished in 1 more day. How long would C alone take?

Competition practiceTime & Work / Pipes
  • A4 1/2 days
  • B6 days
  • C3 days
  • D9 days

Step-by-Step Solution

A and B work 3 days in all: . C did in 1 day, so C alone needs 6 days.
Answer: B) 6 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

15 men working 8 hours a day finish a job in 20 days. How many men are needed to finish…12 men working 8 hours a day dig a 360 m trench in 18 days. In how many days will 16 men…3 men or 5 women can do a job in 12 days. How long will 6 men and 5 women take?2 men and 3 women finish a job in 10 days; 3 men and 2 women finish it in 8 days. How…8 men or 12 women finish a job in 25 days. How long will 6 men and 12 women take?