A completes 7/10 of a work in 14 days and then, with B's help, finishes the rest in 3 days. How long would B alone take to do the whole work?

Competition practiceTime & Work / Pipes
  • A15 days
  • B12 days
  • C18 days
  • D20 days

Step-by-Step Solution

A alone: 20 days. In 3 days A does , so B does in 3 days: B alone 20 days.
Answer: D) 20 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A does 20% of a work in 5 days. B then joins and together they finish the rest in 10…A can finish a task in 10 days working 6 hours a day. B can finish it in 12 days working…A and B can finish a work in 12 days, B and C in 16 days. A works 5 days and B 7 days,…A can finish a work in 12 days and B in 16 days. A starts; A and B work on alternate…A can do a work in 16 days and B in 24 days. A works every day, but B helps only on…