A contractor employs 30 workers to finish in 45 days. After 15 days only one-fourth is done. How many more workers must he hire to finish on time?

Competition practiceTime & Work / Pipes
  • A30 workers
  • B20 workers
  • C10 workers
  • D15 workers

Step-by-Step Solution

worker-days = , so the job is 1800. Left 1350 in 30 days: 45 workers. Hire 15.
Answer: D) 15 workers

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

20 men do 60% of a job in 12 days. How many more men are needed to finish the rest in 4…12 men or 15 women can finish a job in 14 days. How long will 7 men and 5 women take?4 men and 6 women finish a job in 8 days; 3 men and 7 women finish it in 10 days. How…10 workers build a 120 m wall in 12 days working 8 hours a day. How many hours a day…25 men were to finish a job in 30 days. After 20 days only half was done. How many extra…