Step-by-Step Solution
In 18 days 20 workers put in 360 worker-days, and that covered two-fifths of the job, so the whole job is worker-days. Three-fifths, or 540 worker-days, are left and only 12 days remain, so he needs 540 ÷ 12 = 45 workers on site — that is 45 − 20 = 25 extra. 45 is the total workforce required, not the addition asked for. 10 scales the gang by elapsed time against remaining time and ignores that three-fifths of the job is still untouched. 20 simply doubles the gang, which still leaves the job short.
Answer: C) 25