A contractor promised to hand over a job on the 30th day and put 20 equally skilled workers on it. At the end of the 18th day he found that only two-fifths of the job was done. How many extra workers of the same skill must he engage so that the job is still handed over on the 30th day?

Competition practiceTime & Work / Pipes
  • A10
  • B20
  • C25
  • D45

Step-by-Step Solution

In 18 days 20 workers put in 360 worker-days, and that covered two-fifths of the job, so the whole job is worker-days. Three-fifths, or 540 worker-days, are left and only 12 days remain, so he needs 540 ÷ 12 = 45 workers on site — that is 45 − 20 = 25 extra. 45 is the total workforce required, not the addition asked for. 10 scales the gang by elapsed time against remaining time and ignores that three-fifths of the job is still untouched. 20 simply doubles the gang, which still leaves the job short.
Answer: C) 25

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

Cable-laying teams X and Y together can lay a stretch in 9 days; teams Y and Z together…A set of records was to be keyed in by a certain number of clerks in 12 days. Had 4 more…In a day 2 men do as much work as 3 women, and 3 women do as much as 5 children. If 4…Two taps fill a storage drum in 36 minutes and 45 minutes respectively when each works…Kavita is 25% more efficient than Lalit. Working together they finish a stock-taking…