A godown has to be stacked with 6,480 cartons. Each loader stacks 12 cartons per hour of work. If 15 loaders work 9 hours a day, how many days does the stacking take?

Competition practiceTime & Work / Pipes
  • A36 days
  • B4 days
  • C48 days
  • D60 days

Step-by-Step Solution

A day's output is 15 loaders × 9 hours × 12 cartons = 1,620 cartons, so 6,480 ÷ 1,620 = 4 days. 36 divides 6,480 by , which gives the number of working hours, not days, because the 9-hour day has been left out. 48 divides by , dropping the 12 cartons an hour. 60 divides by , dropping the 15 loaders.
Answer: B) 4 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A tank of capacity 7,200 litres stands empty. An inlet delivering 240 litres a minute…Arun can complete a survey on his own in 30 days, and Bipin is 50% more efficient than…Pipe P alone fills a tank in 50 minutes and pipe Q alone empties a full tank in 75…Twelve labourers of equal skill were engaged to finish a job in 20 days. At the end of…An empty cistern can be filled by tap A in 1 hour 12 minutes and by tap B in 1 hour 48…