Twelve labourers of equal skill were engaged to finish a job in 20 days. At the end of the fifth day two of them left and were not replaced. By how many days does the job overrun its 20-day schedule?

Competition practiceTime & Work / Pipes
  • A4 days
  • B3 days
  • C18 days
  • D23 days

Step-by-Step Solution

The job is labourer-days. Five days with twelve men account for 60, leaving 180 for the ten who stay: 180 ÷ 10 = 18 days more, so the job runs 5 + 18 = 23 days in all and overruns by 3 days. 18 days is the closing stretch, not the overrun. 23 days is the new total, again not the overrun. 4 days rescales the whole 20-day schedule by 12/10 to get 24 days, which wrongly applies the reduced gang to the five days already worked at full strength.
Answer: B) 3 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

An empty cistern can be filled by tap A in 1 hour 12 minutes and by tap B in 1 hour 48…Eight machines running 6 hours a day take 15 days to complete an order. How many days…A tank is being filled by a pipe that alone would fill it in 12 hours. Unnoticed, a leak…5 men and 8 women can finish a harvesting job in 6 days, and 4 men and 12 women can also…Taps X, Y and Z alone would fill a tank in 20, 30 and 60 minutes respectively. X and Y…