- A4 days
- B3 days
- C18 days
- D23 days
Step-by-Step Solution
The job is labourer-days. Five days with twelve men account for 60, leaving 180 for the ten who stay: 180 ÷ 10 = 18 days more, so the job runs 5 + 18 = 23 days in all and overruns by 3 days. 18 days is the closing stretch, not the overrun. 23 days is the new total, again not the overrun. 4 days rescales the whole 20-day schedule by 12/10 to get 24 days, which wrongly applies the reduced gang to the five days already worked at full strength.
Answer: B) 3 days