- A12 days
- B15 days
- C27 days
- D18 days
Step-by-Step Solution
The first order costs machine-hours, so an order half as large again costs 1,080 machine-hours. The new set-up supplies machine-hours a day, giving 1,080 ÷ 60 = 18 days. 12 days is 720 ÷ 60 and forgets that the order is larger. 27 days is 1,080 ÷ 40 and keeps the original 8 machines. 15 days assumes the two changes cancel out, but 12 machines at 5 hours is only 60 machine-hours a day against 48 before, a rise of a quarter, while the order rises by a half.
Answer: D) 18 days