Practice30Create account

A workshop's 12 tailors turn out 240 shirts in 5 days. For a fresh order of 480 shirts the strength is raised to 15 tailors, each stitching at the pace of before. How many days does the fresh order need?

Competition practiceTime & Work / Pipes
  • A8 days
  • B4 days
  • C10 days
  • D12.5 days

Step-by-Step Solution

12 tailors over 5 days is 60 tailor-days for 240 shirts, so one tailor stitches 4 shirts a day. 15 tailors therefore stitch 60 shirts a day, and 480 ÷ 60 = 8 days. 10 days doubles the 5 days for the doubled order but forgets the extra tailors. 4 days adjusts for the extra tailors but forgets the doubled order. 12.5 days doubles for the order and then multiplies by 15/12 instead of 12/15, putting the workforce ratio the wrong way up — more tailors must mean fewer days.
Answer: A) 8 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A full tank can be emptied by its outlet in 30 minutes. An inlet that alone would fill…Three welders are hired at ₹900, ₹750 and ₹600 a day. The job runs for 14 days, but the…Naveen alone can compile a report in 24 days and Om alone in 36 days. They compile it on…Three inlets that alone would fill a tank in 30, 20 and 60 minutes are opened together…A contractor agreed to finish a job in 30 days, with a penalty of ₹2,500 for each day…