- A₹25,000
- B₹12,500
- C₹37,500
- D₹50,000
Step-by-Step Solution
In 20 days 24 men put in 480 man-days for half the job, so the whole job is 960 man-days and 480 man-days remain. With 32 men that takes 480 ÷ 32 = 15 days, so the job runs 20 + 15 = 35 days — five days past the agreed 30. The penalty is = ₹12,500. ₹25,000 keeps the original 24 men for the closing stretch (480 ÷ 24 = 20 days, ten days late). ₹37,500 charges the penalty for all 15 days of the closing stretch instead of only the 5 beyond the deadline. ₹50,000 makes both errors at once, charging 20 late days.
Answer: B) ₹12,500