A contractor agreed to finish a job in 30 days, with a penalty of ₹2,500 for each day beyond that. He put 24 men on it, and at the end of the 20th day exactly half the job was done. He then brought in 8 more men of the same skill and the job ran on to its finish. What penalty does he pay?

Competition practiceTime & Work / Pipes
  • A₹25,000
  • B₹12,500
  • C₹37,500
  • D₹50,000

Step-by-Step Solution

In 20 days 24 men put in 480 man-days for half the job, so the whole job is 960 man-days and 480 man-days remain. With 32 men that takes 480 ÷ 32 = 15 days, so the job runs 20 + 15 = 35 days — five days past the agreed 30. The penalty is = ₹12,500. ₹25,000 keeps the original 24 men for the closing stretch (480 ÷ 24 = 20 days, ten days late). ₹37,500 charges the penalty for all 15 days of the closing stretch instead of only the 5 beyond the deadline. ₹50,000 makes both errors at once, charging 20 late days.
Answer: B) ₹12,500

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

Pramod can finish three-eighths of a job in 15 days. Qadir works at one-third of…A, B and C can do a piece of work in 20, 30 and 60 days. In how many days can A do the…A does half as much work as B in three-fourths of the time. If together they take 18…A does a work in 90 days, B in 40 days and C in 12 days. They work one day each in turn,…A completes 7/10 of a work in 14 days and then, with B's help, finishes the rest in 3…