A does a work in 90 days, B in 40 days and C in 12 days. They work one day each in turn, A on day 1, B on day 2, C on day 3, repeating. In how many days is the work done?

Competition practiceTime & Work / Pipes
  • A26 days
  • B28 days
  • C30 days
  • D27 days

Step-by-Step Solution

Each 3-day cycle: . 8 cycles (24 days): . Day 25 (A): +4 = 348; day 26 (B): +9 = 357; day 27 (C) finishes.
Answer: D) 27 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A completes 7/10 of a work in 14 days and then, with B's help, finishes the rest in 3…A does 20% of a work in 5 days. B then joins and together they finish the rest in 10…A can finish a task in 10 days working 6 hours a day. B can finish it in 12 days working…A and B can finish a work in 12 days, B and C in 16 days. A works 5 days and B 7 days,…A can finish a work in 12 days and B in 16 days. A starts; A and B work on alternate…