Pramod can finish three-eighths of a job in 15 days. Qadir works at one-third of Pramod's daily output. How many days would Qadir take to finish the whole job on his own?

Competition practiceTime & Work / Pipes
  • A40 days
  • B45 days
  • C120 days
  • D360 days

Step-by-Step Solution

If three-eighths takes Pramod 15 days, the whole job takes him days, so he does 1/40 of it a day. Qadir does a third of that, 1/120 a day, and needs 120 days. 40 days is Pramod's own figure for the whole job, not Qadir's. 45 days trebles the 15 days, but those 15 days cover only three-eighths of the job. 360 days applies the one-third twice, once in scaling the job up and again in scaling the rate down.
Answer: C) 120 days

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A, B and C can do a piece of work in 20, 30 and 60 days. In how many days can A do the…A does half as much work as B in three-fourths of the time. If together they take 18…A does a work in 90 days, B in 40 days and C in 12 days. They work one day each in turn,…A completes 7/10 of a work in 14 days and then, with B's help, finishes the rest in 3…A does 20% of a work in 5 days. B then joins and together they finish the rest in 10…