4 workers take 15 days to finish a job. To solve for how long 5 workers take, the FIRST correct step is to find the constant product. What is that constant (in worker-days)?

Class 8Direct and Inverse ProportionsDirect and Inverse Proportions
  • A120
  • B66
  • C54
  • D60

Step-by-Step Solution

Workers and days are in inverse proportion, so the product is constant: worker-days. (Then 5 workers take days.)
Answer: D) 60

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Direct and Inverse Proportions practice questions

More Class 8 Direct and Inverse Proportions practice

20 men can dig a canal in 18 days. After working 6 days, 10 more men join. In how many…If two quantities x and y are in direct proportion, then x_1/y_1 equals:If two quantities are in inverse proportion, then the relation between two pairs is:A train running at uniform speed covers 360 km in 4 hours. How far (in km) will it go in…12 pumps can empty a reservoir in 20 hours. How many pumps are needed to empty it in 16…