A and B can finish a job in 36 days. A works twice as fast as B. If B leaves after 12 days, how long does A take to finish?

Class 8Sharing Work and WagesDirect and Inverse Proportions
  • A36 days
  • B24 days
  • C18 days
  • D32 days

Step-by-Step Solution

Rates 2 with , so . After 12 days: done; A at needs days.
Answer: A) 36 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Sharing Work and Wages practice questions

More Class 8 Sharing Work and Wages practice

Working together, A and B do a job in 12 days. A works alone for 6 days, then B joins…Anita and Babli sew uniforms for a school. Anita alone would take 15 days and Babli 10…Kiran and Lata whitewash a boundary wall. The bar shows the wall in equal parts: Kiran…Arjun can finish a job alone in the number of days shown, and so can Bhanu. They do it…Amit and Babu could finish a job alone in the times shown. With the help of Chotu, the…