A job takes A 30 days. A and B together do it in 20 days. What is the ratio of A's work rate to B's?

Class 8Time and WorkDirect and Inverse Proportions
  • A1 : 2
  • B3 : 2
  • C2 : 3
  • D2 : 1

Step-by-Step Solution

; . Ratio . A is the faster worker.
Answer: D) 2 : 1

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time and Work practice questions

More Class 8 Time and Work practice

A can finish a work in 25 days and B in 20 days. They work together for 5 days, then A…A and B finish a job in 9 days. B and C finish it in 12 days. A and C finish it in 18…A alone finishes a job in 15 days; B alone in 10 days. They work on alternate days,…12 women or 8 men can do a job in 30 days. How long will 6 women and 4 men take?On a job, A alone needs 6 days and B alone needs 8 days. They start together; after 2…