12 women or 8 men can do a job in 30 days. How long will 6 women and 4 men take?

Class 8Time and WorkDirect and Inverse Proportions
  • A30 days
  • B15 days
  • C60 days
  • D20 days

Step-by-Step Solution

6 women = half of 12 women; 4 men = half of 8 men. Two half-teams make one full team: 30 days.
Answer: A) 30 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time and Work practice questions

More Class 8 Time and Work practice

On a job, A alone needs 6 days and B alone needs 8 days. They start together; after 2…Aarti paints 1/6 of a wall each day. The bar shows the wall split into one part per day,…The bar models show one whole job. Ravi finishes it in the number of days shown on his…Meena painted a wall alone on day 1; on day 2 Kavya joined her, and both worked at their…A tailoring unit in Tiruppur has three stitching machines. The chart shows how many…