The bar models show one whole job. Ravi finishes it in the number of days shown on his bar and Sohan in the number shown on his. If they work together, in how many days will the job be done?

Class 8Time and WorkDirect and Inverse Proportions
  • A8 days
  • B16 days
  • C3 days
  • D6 days

Step-by-Step Solution

Ravi does of the job a day and Sohan . Together per day, so 3 days.
Answer: C) 3 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time and Work practice questions

More Class 8 Time and Work practice

Meena painted a wall alone on day 1; on day 2 Kavya joined her, and both worked at their…A tailoring unit in Tiruppur has three stitching machines. The chart shows how many…Anil and Bhola start a job together. The timeline shows when Anil leaves; Bhola then…Raju is filling the water tank shown, which already has some water, by carrying buckets…The table shows how long each worker took to do one-fifth of the same job. If Anil, Bala…