A job was planned as shown. After 10 days, 5 more workers joined and everyone worked at the same rate. How many days did the whole job take?

Class 8Workers, Days and HoursDirect and Inverse Proportions
  • A24 days
  • B22 days
  • C16 days
  • D26 days

Step-by-Step Solution

Work left after 10 days worker-days. With 25 workers it takes days, so the whole job takes days.
Answer: D) 26 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Workers, Days and Hours practice questions

More Class 8 Workers, Days and Hours practice

The chart shows the two shifts in a toy factory in Channapatna. Every worker makes toys…The yellow part of the wheat field was harvested by 4 farmers in 3 days. How many days…In Kitchen A, the cooks shown prepare the meals shown in 4 hours. How many cooks does…Crew 1 painted the houses shown in 6 days. How many days will Crew 2 take to paint its…The table shows how many pages each typist typed in a trial and how long it took. If all…