- A15 days
- B22.5 days
- C10 days
- D4 days
Step-by-Step Solution
Crew 1: painter-days for 2 houses, i.e. 12 painter-days per house. Crew 2: 5 houses need 60 painter-days; with 6 painters that is days.
Answer: C) 10 days