A team planned to finish a job in 18 days working 8 hours a day. After 6 days they were asked to finish by day 14, as shown. How many hours a day must the same team now work?

Class 8Workers, Days and HoursDirect and Inverse Proportions
  • A12 hours
  • B10 2/7 hours
  • C10 hours
  • D16 hours

Step-by-Step Solution

Work left team-hours. Days left , so they must work hours a day.
Answer: A) 12 hours

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Workers, Days and Hours practice questions

More Class 8 Workers, Days and Hours practice

A contractor employs 30 workers to finish a road in 40 days. After 10 days, he adds 10…A book has 240 pages and is typed by 5 typists in 12 hours. How long would 8 typists…A team of 20 builds 5 km of road in 10 days. How many workers are needed to build 8 km…A job is planned for 60 workers in 24 days. After 8 days, 20 workers are moved to…4 men or 6 women can finish a job in 15 days. How long would 2 men and 3 women take…