A job is planned for 60 workers in 24 days. After 8 days, 20 workers are moved to another site. How many extra days does the job take beyond the plan?

Class 8Workers, Days and HoursDirect and Inverse Proportions
  • A8 days
  • B16 days
  • C24 days
  • D4 days

Step-by-Step Solution

Left: worker-days with 40 workers = 24 days, not 16. Extra: 8 days.
Answer: A) 8 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Workers, Days and Hours practice questions

More Class 8 Workers, Days and Hours practice

4 men or 6 women can finish a job in 15 days. How long would 2 men and 3 women take…12 cats catch 12 mice in 12 minutes. How many cats are needed to catch 60 mice in 30…20 workers can finish a job in 18 days. They work for 6 days, and then some leave. The…If 9 printers print 900 posters in 5 hours, how long would 6 printers take for 1,200…The pictures show a team of workers, the days of the week they worked on a job, and…