20 workers can finish a job in 18 days. They work for 6 days, and then some leave. The remaining work is done in 16 more days. How many workers left?

Class 8Workers, Days and HoursDirect and Inverse Proportions
  • A4 workers
  • B5 workers
  • C6 workers
  • D8 workers

Step-by-Step Solution

Left after 6 days: worker-days, done in 16 days by workers. So 5 left.
Answer: B) 5 workers

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Workers, Days and Hours practice questions

More Class 8 Workers, Days and Hours practice

If 9 printers print 900 posters in 5 hours, how long would 6 printers take for 1,200…The pictures show a team of workers, the days of the week they worked on a job, and…Team 1 laid the length of road shown. Team 2 works at the same rate per worker per day.…The calendar shows the days on which 8 masons built a compound wall in Lucknow; they do…A job was planned as shown. After 10 days, 5 more workers joined and everyone worked at…