The pictures show a team of workers, the days of the week they worked on a job, and their working hours each day. How many man-hours did the job take?

Class 8Workers, Days and HoursDirect and Inverse Proportions
  • A19 man-hours
  • B48 man-hours
  • C280 man-hours
  • D240 man-hours

Step-by-Step Solution

Count from the picture: 6 workers, 5 days (Mon–Fri) and 9 a.m. to 5 p.m. = 8 hours a day. Man-hours .
Answer: D) 240 man-hours

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Workers, Days and Hours practice questions

More Class 8 Workers, Days and Hours practice

Team 1 laid the length of road shown. Team 2 works at the same rate per worker per day.…The calendar shows the days on which 8 masons built a compound wall in Lucknow; they do…A job was planned as shown. After 10 days, 5 more workers joined and everyone worked at…The chart shows the two shifts in a toy factory in Channapatna. Every worker makes toys…The yellow part of the wheat field was harvested by 4 farmers in 3 days. How many days…