Practice30Create account

A team of 20 builds 5 km of road in 10 days. How many workers are needed to build 8 km in 16 days?

Class 8Workers, Days and HoursDirect and Inverse Proportions
  • A32 workers
  • B25 workers
  • C20 workers
  • D16 workers

Step-by-Step Solution

Worker-days per km: . 8 km: 320 worker-days; workers.
Answer: C) 20 workers

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Workers, Days and Hours practice questions

More Class 8 Workers, Days and Hours practice

A job is planned for 60 workers in 24 days. After 8 days, 20 workers are moved to…4 men or 6 women can finish a job in 15 days. How long would 2 men and 3 women take…12 cats catch 12 mice in 12 minutes. How many cats are needed to catch 60 mice in 30…20 workers can finish a job in 18 days. They work for 6 days, and then some leave. The…If 9 printers print 900 posters in 5 hours, how long would 6 printers take for 1,200…