A contractor employs 30 workers to finish a road in 40 days. After 10 days, he adds 10 more workers. How many MORE days do they need?

Class 8Workers, Days and HoursDirect and Inverse Proportions
  • A30 days
  • B22 1/2 days
  • C20 days
  • D25 days

Step-by-Step Solution

Total 1200 worker-days; 300 done. Left 900 with 40 workers: days.
Answer: B) 22 1/2 days

Master this chapter in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Workers, Days and Hours practice questions

More Class 8 Workers, Days and Hours practice

A book has 240 pages and is typed by 5 typists in 12 hours. How long would 8 typists…A team of 20 builds 5 km of road in 10 days. How many workers are needed to build 8 km…A job is planned for 60 workers in 24 days. After 8 days, 20 workers are moved to…4 men or 6 women can finish a job in 15 days. How long would 2 men and 3 women take…12 cats catch 12 mice in 12 minutes. How many cats are needed to catch 60 mice in 30…