A contractor employs 15 men to finish a job in 30 days. After 24 days he adds 6 men and finishes 1 day early. Had he not added them, how late would the job have been?

Competition practiceTime & Work / Pipes
  • A2 days
  • B3 days
  • COn time
  • D1 day

Step-by-Step Solution

Total work man-days. With 15 men that is 31 days: 1 day late.
Answer: D) 1 day

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

12 men and 18 boys working 7 1/2 hours a day do a job in 60 days. A man does as much as…Three taps together fill a tank in 10 hours. After 2 hours one tap is closed, and the…The total amount of a job completed so far doubles every day, and the job is finished at…A and B together do 3 times as much as C, and B and C together do twice as much as A.…A, B and C take 20, 30 and 60 days. All start; A leaves after 4 days and B after 8 days;…