A job needs 1,500 worker-hours. On day 1, 10 workers work 8 hours; each later day 2 more workers join, all working 8 hours. On which day is the job finished?

Competition practiceTime & Work / Pipes
  • ADay 10
  • BDay 9
  • CDay 11
  • DDay 12

Step-by-Step Solution

Daily hours: 80, 96, 112, …, rising by 16. After 9 days: 1296. Day 10 adds 224, passing 1500.
Answer: A) Day 10

Master this topic in 30 minutes a day.

Don't just memorise the answer — build a daily practice habit.

Practice 5 Similar Questions Free →

All Time & Work / Pipes practice questions

More Time & Work / Pipes practice

A contractor employs 15 men to finish a job in 30 days. After 24 days he adds 6 men and…12 men and 18 boys working 7 1/2 hours a day do a job in 60 days. A man does as much as…Three taps together fill a tank in 10 hours. After 2 hours one tap is closed, and the…The total amount of a job completed so far doubles every day, and the job is finished at…A and B together do 3 times as much as C, and B and C together do twice as much as A.…